Client Testimonials


  1. Home
  2. |
  3. 
Client Testimonials


What some of our clients are saying

TSF / Concrete Civils, Youga Gold Mine, Burkina Faso (2007)

PW was selected in 2006 for the construction of the Tailings Storage Facility at the new Youga Gold Mine Project in Burkina Faso. This contract was extended thereafter to include a portion of the Plant Site Concrete Civils. PW constructed the Primary Crusher Bin, Ball Mill superstructure, foundations for secondary crushers, and other miscellaneous items. PW worked on site from Dec 2006 to Dec 2007 in this scope of civil engineering work, while also mobilising and commencing Contract Mining work. Throughout the project PW have at all times provided a professional, competent and efficient service with a partnership approach to the day to day activities and interfaces with our construction project management team and our mining department, contributing to a smooth running operation.

Bob Harris

Vice President of Operations, Burkina Mining Company

TSF / Concrete Civils, Youga Gold Mine, Burkina Faso (2007)

PW was selected in 2006 for the construction of the Tailings Storage Facility at the new Youga Gold Mine Project in Burkina Faso. This contract was extended thereafter to include a portion of the Plant Site Concrete Civils. PW constructed the Primary Crusher Bin, Ball Mill superstructure, foundations for secondary crushers, and other miscellaneous items. PW worked on site from Dec 2006 to Dec 2007 in this scope of civil engineering work, while also mobilising and commencing Contract Mining work. Throughout the project PW have at all times provided a professional, competent and efficient service with a partnership approach to the day to day activities and interfaces with our construction project management team and our mining department, contributing to a smooth running operation.

Bob Harris

Vice President of Operations, Burkina Mining Company

TSF / Concrete Civils, Youga Gold Mine, Burkina Faso (2007)

PW was selected in 2006 for the construction of the Tailings Storage Facility at the new Youga Gold Mine Project in Burkina Faso. This contract was extended thereafter to include a portion of the Plant Site Concrete Civils. PW constructed the Primary Crusher Bin, Ball Mill superstructure, foundations for secondary crushers, and other miscellaneous items. PW worked on site from Dec 2006 to Dec 2007 in this scope of civil engineering work, while also mobilising and commencing Contract Mining work. Throughout the project PW have at all times provided a professional, competent and efficient service with a partnership approach to the day to day activities and interfaces with our construction project management team and our mining department, contributing to a smooth running operation.

Bob Harris

Vice President of Operations, Burkina Mining Company

MPS Container Terminal, Tema Port, Ghana (2008)

In 2005, Meridian Port Services Ltd commenced the onsite phase of the AreaB Container Terminal project in the port of Tema. A tender for the enabling works and demolitions was won by PW Ghana Ltd and physical work started on site in June of that year. Thereafter, the main contract for the design and construction of the Area B Container Terminal was also won by PW Ghana Ltd, after a process of competitive tender. The construction operations commenced on site in August 2006. The work was carried out on a Brownfield site within a live and busy Port. The construction work was carried out efficiently at all times. Sections of the site were progressively handed over to MPS by PW Ghana Ltd. The work progressed without any Health & Safety accidents, and the final quality was achieved to specified requirements.

Mohamed Samara

CEO, MPS Ltd.

MPS Container Terminal, Tema Port, Ghana (2008)

In 2005, Meridian Port Services Ltd commenced the onsite phase of the AreaB Container Terminal project in the port of Tema. A tender for the enabling works and demolitions was won by PW Ghana Ltd and physical work started on site in June of that year. Thereafter, the main contract for the design and construction of the Area B Container Terminal was also won by PW Ghana Ltd, after a process of competitive tender. The construction operations commenced on site in August 2006. The work was carried out on a Brownfield site within a live and busy Port. The construction work was carried out efficiently at all times. Sections of the site were progressively handed over to MPS by PW Ghana Ltd. The work progressed without any Health & Safety accidents, and the final quality was achieved to specified requirements.

Mohamed Samara

CEO, MPS Ltd.

MPS Container Terminal, Tema Port, Ghana (2008)

In 2005, Meridian Port Services Ltd commenced the onsite phase of the AreaB Container Terminal project in the port of Tema. A tender for the enabling works and demolitions was won by PW Ghana Ltd and physical work started on site in June of that year. Thereafter, the main contract for the design and construction of the Area B Container Terminal was also won by PW Ghana Ltd, after a process of competitive tender. The construction operations commenced on site in August 2006. The work was carried out on a Brownfield site within a live and busy Port. The construction work was carried out efficiently at all times. Sections of the site were progressively handed over to MPS by PW Ghana Ltd. The work progressed without any Health & Safety accidents, and the final quality was achieved to specified requirements.

Mohamed Samara

CEO, MPS Ltd.

Sansu TSF Rehabilitation Project, Obuasi Gold Mine, Ghana (2008)

We, as the consultants to AGA on the Sansu Project at Obuasi, were most impressed with your performance. PW Ghana Ltd delivered a job well done under sometimes difficult climatic conditions. You kept to your time schedule, and we were also impressed by the open lines of communication you maintained from the remote site to Johannesburg.

Dr. Fritz Wagener (Pr Eng)

Sansu TSF Rehabilitation Project, Obuasi Gold Mine, Ghana (2008)

We, as the consultants to AGA on the Sansu Project at Obuasi, were most impressed with your performance. PW Ghana Ltd delivered a job well done under sometimes difficult climatic conditions. You kept to your time schedule, and we were also impressed by the open lines of communication you maintained from the remote site to Johannesburg.

Dr. Fritz Wagener (Pr Eng)

Sansu TSF Rehabilitation Project, Obuasi Gold Mine, Ghana (2008)

We, as the consultants to AGA on the Sansu Project at Obuasi, were most impressed with your performance. PW Ghana Ltd delivered a job well done under sometimes difficult climatic conditions. You kept to your time schedule, and we were also impressed by the open lines of communication you maintained from the remote site to Johannesburg.

Dr. Fritz Wagener (Pr Eng)

Tullow Airbase Yard Phase 1, Takoradi, Ghana (2009)

PW showed a great willingness to comply with existing safety management systems and personal safety requirements that existed at the Tullow site. On arrival not only was a full scope of work presented but also a full catalogue of applicable risk assessments that were of a very high standard and most importantly were followed to the letter.

Brian Nicoll

EHS Advisor, Tullow

Tullow Airbase Yard Phase 1, Takoradi, Ghana (2009)

PW showed a great willingness to comply with existing safety management systems and personal safety requirements that existed at the Tullow site. On arrival not only was a full scope of work presented but also a full catalogue of applicable risk assessments that were of a very high standard and most importantly were followed to the letter.

Brian Nicoll

EHS Advisor, Tullow

Tullow Airbase Yard Phase 1, Takoradi, Ghana (2009)

PW showed a great willingness to comply with existing safety management systems and personal safety requirements that existed at the Tullow site. On arrival not only was a full scope of work presented but also a full catalogue of applicable risk assessments that were of a very high standard and most importantly were followed to the letter.

Brian Nicoll

EHS Advisor, Tullow

Golden Jubilee Terminal, Paving Project, Tema Port, Ghana (2009)

During the year 2008, the Ghana Ports and Harbours Authority (GPHA) carried out the Upgrade and Repair of the Golden Jubilee Terminal (GJT) Pavement at Tema Port whilst the terminal was in use. PW Ghana Limited was awarded a portion of this contract to execute. The mobilization to site, the commencement of construction was efficiently carried out and all the interfaces and the restrictions of the operational terminal were observed to GPHA’s satisfaction. The work progressed without any health and safety incidents, and the final quality was achieved to specification. Lines of communication between our operational staff and PW staff were cordial and responsive at all times. The project was successfully completed and we therefore recommend PW to any company or institution that may need its services.

N.P. Galley

Director General, GPHA

Golden Jubilee Terminal, Paving Project, Tema Port, Ghana (2009)

During the year 2008, the Ghana Ports and Harbours Authority (GPHA) carried out the Upgrade and Repair of the Golden Jubilee Terminal (GJT) Pavement at Tema Port whilst the terminal was in use. PW Ghana Limited was awarded a portion of this contract to execute. The mobilization to site, the commencement of construction was efficiently carried out and all the interfaces and the restrictions of the operational terminal were observed to GPHA’s satisfaction. The work progressed without any health and safety incidents, and the final quality was achieved to specification. Lines of communication between our operational staff and PW staff were cordial and responsive at all times. The project was successfully completed and we therefore recommend PW to any company or institution that may need its services.

N.P. Galley

Director General, GPHA

Golden Jubilee Terminal, Paving Project, Tema Port, Ghana (2009)

During the year 2008, the Ghana Ports and Harbours Authority (GPHA) carried out the Upgrade and Repair of the Golden Jubilee Terminal (GJT) Pavement at Tema Port whilst the terminal was in use. PW Ghana Limited was awarded a portion of this contract to execute. The mobilization to site, the commencement of construction was efficiently carried out and all the interfaces and the restrictions of the operational terminal were observed to GPHA’s satisfaction. The work progressed without any health and safety incidents, and the final quality was achieved to specification. Lines of communication between our operational staff and PW staff were cordial and responsive at all times. The project was successfully completed and we therefore recommend PW to any company or institution that may need its services.

N.P. Galley

Director General, GPHA

Adjen Kotoku Road Works, Ghana, (2010)

With the construction of Road Works and Taxi Rank at Adjen Kotoku now completed, we write to congratulate PW Ghana Ltd on a very well executed project. PW’s attitude to safety, the professionalism and the dedication shown by your whole site team which often exceeded over hundred and fifty people (150) people on a daily basis during the 7 month campaign was exemplary and the quality of work, as verified by our consulting engineers was faultless. There were no lost Time Injuries (LTl’s) reported in all shifts worked, often in difficult circumstances

Jan De Roeck

Resident Manager, Dredging International Services

Adjen Kotoku Road Works, Ghana, (2010)

With the construction of Road Works and Taxi Rank at Adjen Kotoku now completed, we write to congratulate PW Ghana Ltd on a very well executed project. PW’s attitude to safety, the professionalism and the dedication shown by your whole site team which often exceeded over hundred and fifty people (150) people on a daily basis during the 7 month campaign was exemplary and the quality of work, as verified by our consulting engineers was faultless. There were no lost Time Injuries (LTl’s) reported in all shifts worked, often in difficult circumstances

Jan De Roeck

Resident Manager, Dredging International Services

Adjen Kotoku Road Works, Ghana, (2010)

With the construction of Road Works and Taxi Rank at Adjen Kotoku now completed, we write to congratulate PW Ghana Ltd on a very well executed project. PW’s attitude to safety, the professionalism and the dedication shown by your whole site team which often exceeded over hundred and fifty people (150) people on a daily basis during the 7 month campaign was exemplary and the quality of work, as verified by our consulting engineers was faultless. There were no lost Time Injuries (LTl’s) reported in all shifts worked, often in difficult circumstances

Jan De Roeck

Resident Manager, Dredging International Services

Sierra Rutile Project, Sierra Leone (2011)

PW has carried out this work to the appropriate standard in an efficient and professional manner. The onsite management has been co-operative and accommodating of SRL requests. In addition, PW have willingly assisted with machinery and operators during difficult production periods at the mine.

Mark Button Chief

Operating Officer, Sierra-Rutile Limited

Sierra Rutile Project, Sierra Leone (2011)

PW has carried out this work to the appropriate standard in an efficient and professional manner. The onsite management has been co-operative and accommodating of SRL requests. In addition, PW have willingly assisted with machinery and operators during difficult production periods at the mine.

Mark Button Chief

Operating Officer, Sierra-Rutile Limited

Sierra Rutile Project, Sierra Leone (2011)

PW has carried out this work to the appropriate standard in an efficient and professional manner. The onsite management has been co-operative and accommodating of SRL requests. In addition, PW have willingly assisted with machinery and operators during difficult production periods at the mine.

Mark Button Chief

Operating Officer, Sierra-Rutile Limited

Chemical Storage & Decanting Facility, Takoradi Port, Ghana (2011)

In order to support our offshore production operations, in 2010, Tullow commissioned PW Ghana Ltd to carry out the design (civil / piping / electrical engineering) and construction of the Chemical Storage and Decanting Facility located in Takoradi Port. Tullow were pleased to receive from PW another quality facility, completed in good time, without a single Lost Time Incident, and within the budgeted cost.

Dai Jones

Chemical Storage & Decanting Facility, Takoradi Port, Ghana (2011)

In order to support our offshore production operations, in 2010, Tullow commissioned PW Ghana Ltd to carry out the design (civil / piping / electrical engineering) and construction of the Chemical Storage and Decanting Facility located in Takoradi Port. Tullow were pleased to receive from PW another quality facility, completed in good time, without a single Lost Time Incident, and within the budgeted cost.

Dai Jones

Chemical Storage & Decanting Facility, Takoradi Port, Ghana (2011)

In order to support our offshore production operations, in 2010, Tullow commissioned PW Ghana Ltd to carry out the design (civil / piping / electrical engineering) and construction of the Chemical Storage and Decanting Facility located in Takoradi Port. Tullow were pleased to receive from PW another quality facility, completed in good time, without a single Lost Time Incident, and within the budgeted cost.

Dai Jones

© copyright 2024 PW Mining International

Website powered by Exceed

© copyright 2024 PW Mining International

Website powered by Exceed